Pareora Pipeline

LOWER PAREORA GEORGE TO CLAREMONT
- PIPELINE RENEWAL STAGE 3

Subcontractor

The Pareora pipeline is a strategically important water supply asset for the Timaru district. It provides a gravity supply of up to 215 L/s from the Pareora River to the Claremont Reservoir. The Pareora pipeline is a critical component of the Timaru water supply, providing the bulk transfer of raw water from the Pareora River intake to the Claremont water treatment plant and storage reservoirs.

Total Spec Engineering undertook:

  • 150m bridge crossing

  • Air valve sections

  • PRV chambers

  • 6x culvert crossings

  • Flow meter spools

  • All stainless steel work and bridge crossings

  • Scour valve spools and grates

  • Fabrication of structural bridge components